The dispute between the Ministry of Public Works (MOPC) and the construction company Mota Engil over the Metrobus project concluded with the Arbitral Tribunal ruling against the Paraguayan State for executing the insurance policy against the Tribunal's order and for delays in the project's execution schedule.
Asunción, Agencia IP.- The dispute between the Ministry of Public Works (MOPC) and the construction company Mota Engil over the Metrobus project concluded with the Arbitral Tribunal ruling against the Paraguayan State for executing the insurance policy against the Tribunal’s order and for delays in the project’s execution schedule.
General Prosecutor Marco Aurelio González announced the verdict yesterday at a press conference, describing it as a «negligent performance» by the Government’s previous administration.
For the execution of the insurance policy against the Tribunal’s explicit order, the State must return approximately $5 million, plus $1 million in interest, an increase in legal costs for this action, and a payment of $2.8 million to Mota Engil for amounts wrongfully withheld.
The Tribunal ruled that the MOPC was 37% responsible for the delay in the works, and an additional $5 million must be paid. Mota Engil attributed the delay to the State for 691 days, of which the Tribunal found the MOPC responsible for 258 days.